25 June 2010 (Friday)

We went to PAn Sheng Developement project of 2 storey Terrace House. We were accompanied by Mrs. Nurziah, Mrs. Ima and Mr. Fabian. We came there to watch how the piling process works.

- As i mentioned before, the project use Bakau pile instead of RC piles.
-For Bakau pile,it is important to determine the ground water table as Bakau stays good if there is water.
- Surface of the cross-section will be cut smoothly without any angle to avoid slippery during attachment.








- Piling machine with a 1 Tan Hammer.














- Using only the piling machine, to carry the bakau to the piling point shows the efficiency of using what they have around them.












-Working on the pile sleeves, attached for the the incoming Bakau.

















- A worker marked on the pile, maximum setting blow. From the marking point, they will calculate the settlement of a total 10 blow to determine the maximum hard stratum/ground.

24 June 2010 (Thursday)

-Assist BD department to called on Borneo Group S/B, requesting paper to paper printing of a drawing plan. Later on, representative came to collect the original drawing plan. It took 2 hours for Borneo Group to print and send it back to us.


-Assisted the other trainee to stamp a total of 10 drawings.
-Suspected stamp.

-Update my report.

23 June 2010 (Wednesday)

-Doing the same task as before, photocopying, faxing, distribution of letters, and etc.
-updating my report.

-We went to Lok Kawi Heights with the other SUDC's Staff to send the model house of Saujana Impian project.

22 June 2010 (Tuesday)

-Continue with my structural designing check. Apart from that, I was given the oppurtunity to try out the software "ProCon".

-Basically, ProCon is a software used by the engineers to analyzed components of structure.
-Different with Esteem, ProCon can only analyzed limited number of structure components.

21 June 2010 (Monday)

- In the morning, went to Kingfisher semi-detached 2 storey house, on a joint inspection with Pan Sheng S/B. We SUDC as the land owner are joint venturing with Pan Sheng (Developer). These are some arguements happens during the inspection between SUDC and Pan Sheng as the developer. Since SUDC were the land owner, we were given the royalty in a sum of 28 units houses.

The purchaser of unit 5 and unit 7 came with us to inspect together. There's a lot of defects founded, but Pan Sheng doesn't want to take responsibility, since the liberty period has already ended. Most of the defects are caused by bad workmanship.

Hence SUDC agreed to do all the rectification work. We appointed our contractor to do the work. Here, in the picture, we can see Mr. Lim were discussing with the purchaser.

























SUDC foreman are inspecting for any problem causing the leak at the car-posh ceiling.













-Later on we went to SabaConcrete S/B. This time we're gonna do the test cube testing on our own. The cube we used for testing was not the concrete for any of SUDC's project. But it was especially made for our testing. There were a total of 3 grade 3o concrete cubes. All of them were 7 days old. We then do the calculation to determine the strength of the concrete. It was quite challenging because all the explanation were in Malay.

-Observe how the concrete were mix from a silo, to the lorry mixer for transportation to the construction site.

18 June 2010 (Friday)

I'm one leave for half day. One of my grandmother pass away earlier this morning. so I'll be back to my office only in the after noon. As promised before, Dr. Fathoni came to visit me. We discussed a lot in the matter of my points regarding my Internship in SUDC. Mrs. Nurziah as the representative from project Department, ob behalf of Mrs. Kalsum act as my supervisor for that day.

- other then welcoming my lecturer from Uniten, I managed to help Mrs. Fatimah (Executive Assistant Administration) to print out a total of 100 pages of certificate for tonight's event.


Tuesday, June 22, 2010

16June 2010 (Wednesday)

-Continue with structural Design check, for the same project but differrent section of structure.

-Assist Mr.Ali Hassan to divide an area in a drawing plan into 2 lots, (Lot A & Lot B). We used AutoCad for this task. It was quite challenging since the drawing plan was a photocopy, hence the coordinate seems divisible.